i. Section 25(1)(b) requires that “the procuring entity, having procured goods, works or services from a contractor, determines that additional supplies must be procured from that contractor”. Therefore, the PE’s justification should demonstrate this prerequisite, which is that a contract would have had to be previously initiated with the contractor in question, for the supply of staff uniforms, to then make the case for additional goods.