1. Home
  2. /
  3. Knowledge Center
  4. /
  5. Responsiveness of Bids 1
KNOWLEDGE CENTRE
< All Topics
Print

Responsiveness of Bids 1

  1. A Procuring Entity (PE) initiated procurement proceedings through the deployment of the restricted bidding procurement method, for the procurement of consulting services; 
  2. Five individual consultants were invited to submit proposals;
  3. At the close of tender, one bid was received;
  4. It was a condition of the bidding document that bidders must submit a valid Tax Compliance Letter (TCL);
  5. The sole bidder submitted a TCL belonging to the Company / Consulting Firm owned by the individual consultant and not a TCL in his own name;
  6. The PE seeks advice on whether TCL should be accepted.

Previous Responsiveness of Bid 3
Table of Contents